Wind Power Project Plan - School Sites
1 Team and Consultant Source Selection
1.1 Confirm
technical expertise required by the team
1.2 Issue
Consultant RFP
1.3 Source select
consultants with defined responsibilities for each consultant
1.4 Inform
selected consultants
1.5 Execute
contract(s)
2 Collect, Review and Analyze
Electrical Supply and Demand Data
2.1 Collect Electrical Data
2.2.1 Relate
changes in operations that may change electric consumption. (e.g., equipment
additions, building additions, multiple shifts)
2.2.2 Analyze
current energy use and on-site energy production opportunities:
2.2.3 Collect
data on monthly consumption.
2.2.4 Research
likely future energy procurement method and terms (e.g., competitive supplier
long-term contract, standard offer).
This will provide estimates to future value of displaced energy.
2.2.4 Analyze
energy consumption data at monthly level of detail including kWh consumption,
and peak kW draw.
2.2 Populate data repository with electrical supply and
demand data tables, graphs and graphics
3 Site
Physical Evaluation & Potential Wind Turbine Locations
3.1 Collect site plans: building, electrical, plot, septic,
confirm ownership structure
3.2 Detailed site inspection
3.1.1 Examine energy systems, both in-house, and
utility owned. Document description of current energy infrastructure will
include electrical transformers,
electric panels, wiring configuration.
3.1.2 Identify
sensitive environmental areas
3.1.3 Scope
preliminary location(s) for a wind turbine, exact locations will be detailed
via GPS.
3.1.4 Identify
proximity to neighboring properties;
3.1.5 Consider
project lay down area requirements and
construction
logistics
3.2 Photo simulations
3.2.1 Review
photo simulations already developed
3.2.2 Determine
additional photo simulations required
3.2.3 Conduct
additional photo simulations as required
3.3.2 Select
photosimulations for Public Information Plan
3.3 List and resolve of
potential site issues
3.3.1 FAA Requirements
3.3.1 Zoning requirements (noise, proximity to
abutters, proximity to schools buildings and student use areas outside)
4 Create
Base Concept Cases (e.g., scenarios) for Different Technologies.
10.1 Chose Site and Turbine Equipment Size
10.2 Develop scenarios for wind turbine installation
10.3 Select most promising site (middle school or high
school)
10.4 Review and choose best wind turbine. Given the energy consumption
and wind resources we will choose wind turbine systems (likely between 600 kW
and 750 kW for two school scenario or 1.5 MW for single school option).
10.4.1Various manufacturer tower heights will be
analyzed. 10.5 Determine
projected lead times required for turbine order
5 Bond Referendum
5.1 Referendum Authority
5.1.1 Draft Legislation
5.1.2 TC
Approval
5.1.3 Introduced as Bill
5.1.4 Bill
Passed
4.2 Conduct Referendum
4.2.1 TC Approval and Set Date
4.2.3 Conduct
Ballot
6 Site Ownership, Environmental Impacts
and Regulatory Analysis
6.1 Research and analyze required permits, licenses and
approvals. Special emphasis will be placed on FAA approval given proximity of
middle school to
6.2 Verify site ownership and verify plots
6.3 Identify abutting properties and ownership. Determine
if properties interfere with proposed site installation.
6.3.1 Incorporate
abutter issues into Community Issues Analysis
6.4 Identify and analyze migratory birds and wildlife
impact
6.4.1 Provide notice to USFWS and RI Natural
Heritage programs regarding potential threatened and endangered species and/or
critical habitat
6.5 Identify and analyze Human Health and Safety Issues
6.6 Analyze required environmental approvals and permits,
processes and procedures and timeframes
6.7 Develop a Plan of Action with milestones to obtain all siting, environmental approvals and regulatory permits
7 Physical/Electrical Technical
Feasibility Analysis
7.2 Geotechnical/Physical.
7.2.1 Identify and incorporate any available
studies performed on the proposed school sites.
7.2.2. Identify and resolve geotechnical issues
7.3 Electrical.
7.3.1 Analyze the electrical interconnection
requirements of the supplying electric utility and specify the characteristics
of the required wire runs, protective relays, transformers, and metering. Provide a one-line diagram for the most
promising location.
7.4 Construction Staging / Erection. Appropriate staging
areas will be assessed. Erection needs,
including crane capacities will be determined.
8. Wind Resource Assessment
(Contractor)
8.1 Contractor Perform Wind Resource Assessment.
8.2 Contractor Provide Wind Resource Model
9. Economic Feasibility Analysis
(Contractor Assisted)
9.1 Determine expected sources of funding and ownership
9.2 Research and estimate likely revenue from REC sales
9.3 (Contractor) Research and collect for major scenarios
major costs. Estimated costs will be
collected in parallel to the technical analysis. Major costs (e.g., turbine, tower,
transformer, construction, operations and maintenance) will be estimated for
each wind turbine system. Differences in
costs for a specific site also will be considered.
8.4 (Contractor) Incorporate project costs, financing
costs, energy production, avoided utility costs, excess production wholesale
sales, and ownership
structure into pro forma cash flow analysis.
8.5 (Contractor) Develop an economic model that can be used
for sensitivity analysis.
8.6 Run scenarios and sensitivity analysis using the
contractor-provided economic model and contractor-provided wind resource data.
10 Community Perception
and Education Plan
10.1 Design public opinion surveys.
10.2 Conduct Public Opinion Forums
- Positive perceptions to build upon.
- Negative perceptions to correct.
10.3 Develop a pubic relations and education plan for use
prior to the referendum ballot.
11 Develop and Publish a Feasibility
Study Report
11.1 Prepare draft report of summary and recommendations
11.2 Brief and obtain advisory opinions from the Town Planning
and Zoning Board
11.3 Present Study Report to Town Council
12 Obtain Town Council and School
Committee Approval to Proceed with Plan
12.1 Draft approval resolution
12.2 Present resolution to TC
12.3 Present resolution to SC
13 Initiate
Wind Power Project Implementation
13.1 Initiate Regulatory Approvals
13.2
Initiate Project Funding
13.3 RFP for Wind Turbine
<